Hunter Environmental was contracted by ESM Power to deliver the construction of the 132kV substation for the Doverdale Solar Farm.

The scope of works included:

  • Cut-and-fill earthworks
  • Installation of reinforced concrete structures
  • Ducting Installation
  • Drainage systems
  • Shell and core construction of a brick-built control building
  • Precast retaining walls
  • Hard landscaping and topsoiling
  • Handrail installation

Additionally, Hunter Environmental fulfilled all plant requirements for our client through our sister company, Hunter Plant Hire.

Collaborating with Hunter Environmental on our renewable energy infrastructure project was a seamless and rewarding experience. Their team brought a rare combination of technical expertise with environmental awareness. From site development to final commissioning, their commitment to quality, safety, and sustainability was evident in every phase. We confidently recommend Hunter Environmental to any organization working on large scale infrastructure projects.

Daniel Russell - PBM Group